An ongoing solar PV programme for Sanctuary Housing delivered on the Fortem framework, requiring scaffolding access at a sustained rate of 100+ properties per month. Maintaining that volume demands crew depth, reliable mobilisation, and sequencing tightly coordinated with the PV installation teams across a continuous rolling programme.
SSG Scaffolding provided roof access and edge protection at programme scale, sequenced with the installation teams and delivered as a continuous rolling operation. Resident-safe systems, statutory inspection, and per-property records were maintained throughout.
Sustained delivery at 100+ properties per month, with consistent on-time, zero-incident performance - evidence of the operational scale that distinguishes SSG Scaffolding on volume social housing programmes.